Up to May Half Term

Borras Construction are currently completing the brickwork up to Finished Floor Level (DPC level). The floor reinforcement has now been installed, and we are currently awaiting the concrete delivery for the floor slab.

The concrete will be left to cure over the bank holiday weekend, and works will resume on Tuesday with the continuation of the brickwork and blockwork. Scaffold installation is planned for the next couple of weeks.

During the school holidays, we are also planning to install ducting near the main hall to allow the new building to be connected to the existing building for electricity and data services. This work will involve the temporary removal and reinstatement of some paving slabs.